Forecasted Yearling Chinook Snake R All Spr/Sum Wild Query Parameters | |
Year | 2019 |
Project | John Day |
River Parameter | Temperature |
Critical Temperature Value | 15 C |
Calculate Exposure | Above Critical Value |
River Parameter Data Fill | No |
Query Dates | 1/1 - 12/31 |
Forecast Date | Aug 10, 2019 |
Total Run Period (Mar 25 - Aug 30) | |
Temperature Exposure Index | 13.16 C |
Percent of Fish Exposed | 6.5 % |
Number of Days Fish Exposed | 43 |
Middle 80% of Run Period (May 4 - May 31) | |
Temperature Exposure Index | 13.04 C |
Percent of Fish Exposed | 0 % |
Number of Days Fish Exposed | 0 |
Middle 50% of Run Period (May 10 - May 24) | |
Temperature Exposure Index | 13.17 C |
Percent of Fish Exposed | 0 % |
Number of Days Fish Exposed | 0 |
Run Dates | |
First Day of Run | Mar 25 |
5% of Run passed | May 1 |
10% of Run passed | May 4 |
50% of Run passed | May 15 |
90% of Run passed | May 31 |
95% of Run passed | Jun 5 |
Last Day of Run | Aug 30 |
Date(s) When Temperature Crosses 15 C | |
Jun 3 |