Columbia Basin Performance Measures

PIT Tag Exposure Results

graph

PIT-Tagged Wild Summer Steelhead Query Parameters
Year2020
ProjectIce Harbor
River ParameterTailrace TDG Percent
Critical Tailrace TDG Percent Value120 %
Calculate ExposureAbove Critical Value
River Parameter Data FillNo
Query Dates1/1 - 12/31
Total Run Period (Mar 31 - Jun 28)
Total Number of Fish Observed383
Percent of Total Run Analyzed [Number Observed]100 % [383]
Tailrace TDG Percent Exposure Index119.78 %
Percent of Fish Exposed [Number Exposed]42.5 % [163]
Number of Days Fish Exposed20
Middle 80% of Run Period (Apr 30 - May 27)
Number of Fish Observed311
Percent of Middle 80% of Run Analyzed [Number Observed]100 % [311]
Tailrace TDG Percent Exposure Index120.12 %
Percent of Fish Exposed [Number Exposed]42.1 % [131]
Number of Days Fish Exposed11
Middle 50% of Run Period (May 6 - May 23)
Number of Fish Observed196
Percent of Middle 50% of Run Analyzed [Number Observed]100 % [196]
Tailrace TDG Percent Exposure Index120.3 %
Percent of Fish Exposed [Number Exposed]44.8 % [88]
Number of Days Fish Exposed7
Run Dates
First Day of RunMar 31
5% of Run passedApr 25
10% of Run passedApr 30
50% of Run passedMay 17
90% of Run passedMay 27
95% of Run passedMay 30
Last Day of RunJun 28
Date(s) When Tailrace TDG Percent Crosses 120 %
May 1, May 3, May 4, May 5, May 12, May 13, May 14, May 15, May 19, May 25, May 28, Jun 7, Jun 8, Jun 9