Forecasted Steelhead Snake R Wild Query Parameters | |
Year | 2020 |
Project | Lower Monumental |
River Parameter | TDG Percent |
Critical TDG Percent Value | 120 % |
Calculate Exposure | Above Critical Value |
River Parameter Data Fill | No |
Query Dates | 1/1 - 12/31 |
Forecast Date | Jul 21, 2020 |
Total Run Period (Feb 24 - Aug 13) | |
TDG Percent Exposure Index | 121.27 % |
Percent of Fish Exposed | 98.3 % |
Number of Days Fish Exposed | 57 |
Middle 80% of Run Period (May 4 - Jun 3) | |
TDG Percent Exposure Index | 121.31 % |
Percent of Fish Exposed | 100 % |
Number of Days Fish Exposed | 31 |
Middle 50% of Run Period (May 11 - May 29) | |
TDG Percent Exposure Index | 121.31 % |
Percent of Fish Exposed | 100 % |
Number of Days Fish Exposed | 19 |
Run Dates | |
First Day of Run | Feb 24 |
5% of Run passed | May 1 |
10% of Run passed | May 4 |
50% of Run passed | May 22 |
90% of Run passed | Jun 3 |
95% of Run passed | Jun 7 |
Last Day of Run | Aug 13 |
Date(s) When TDG Percent Crosses 120 % | |
Apr 24, Jun 21 |