PIT-Tagged Wild Summer Steelhead Query Parameters | |
Year | 2020 |
Project | McNary |
River Parameter | Tailrace TDG Percent |
Critical Tailrace TDG Percent Value | 120 % |
Calculate Exposure | Above Critical Value |
River Parameter Data Fill | No |
Query Dates | 1/1 - 12/31 |
Total Run Period (Mar 22 - Jun 21) | |
Total Number of Fish Observed | 476 |
Percent of Total Run Analyzed [Number Observed] | 100 % [476] |
Tailrace TDG Percent Exposure Index | 116.34 % |
Percent of Fish Exposed [Number Exposed] | 35.7 % [170] |
Number of Days Fish Exposed | 27 |
Middle 80% of Run Period (Apr 5 - May 27) | |
Number of Fish Observed | 391 |
Percent of Middle 80% of Run Analyzed [Number Observed] | 100 % [391] |
Tailrace TDG Percent Exposure Index | 117.14 % |
Percent of Fish Exposed [Number Exposed] | 34.7 % [136] |
Number of Days Fish Exposed | 17 |
Middle 50% of Run Period (Apr 10 - May 16) | |
Number of Fish Observed | 249 |
Percent of Middle 50% of Run Analyzed [Number Observed] | 100 % [249] |
Tailrace TDG Percent Exposure Index | 118.37 % |
Percent of Fish Exposed [Number Exposed] | 24.8 % [62] |
Number of Days Fish Exposed | 6 |
Run Dates | |
First Day of Run | Mar 22 |
5% of Run passed | Apr 2 |
10% of Run passed | Apr 5 |
50% of Run passed | May 5 |
90% of Run passed | May 27 |
95% of Run passed | Jun 2 |
Last Day of Run | Jun 21 |
Date(s) When Tailrace TDG Percent Crosses 120 % | |
May 11, Jun 16 |